Please be advised that JCP&L will have large vehicles delivering crane parts and a transformer to the Deep Run Substation located at the end of First Place today, Thursday April 15th 2021, between the hours of 11:00 A.M. and 2:00 P.M. On Friday April 16, 2021, the transformer will be placed on it’s foundation and the trucks will exit the area between approximately 10:00 A.M. and 2:00 P.M. On approximately Tuesday April 20, 2021 JCP&L will have 3 trucks access the area and leave the next day. If you have any questions please call James Markey of JCP&L at 732-723-6652.