The guiderail installation on the Route 9 corridor of Old Bridge began on Monday evening. The team is working hard and averaging approximately 800 feet a night. It is estimated work will continue for 3 weeks; barring any unforeseen conditions and weather dependent. The attached photos were received this morning from the field team of the project’s progress.
![The guiderail installation on the Route 9 corridor of Old Bridge began on Monday evening.](https://core-docs.s3.amazonaws.com/old_bridge_township%2C_nj_ar/article/image/large_8d7e0f7b-b084-4922-8fbd-5d66b756c680.jpg)
The guiderail installation on the Route 9 corridor of Old Bridge began on Monday evening.
June 7, 2023